kVA Tools logokVATools.io ❯ Standby Planner


Standby Planner

Technical Documentation and Calculation Methodology

1. Introduction

The Standby Planner determines the minimum nameplate kVA and kW rating required for a standby or emergency generator to serve a defined load. The tool evaluates three independent sizing constraints simultaneously — running load demand, motor starting voltage dip, and step load acceptance — and identifies whichever constraint requires the largest machine. This multi-constraint approach reflects actual engineering practice and prevents the most common generator sizing error, which is optimising for running load alone and discovering on commissioning day that the largest motor will not start within acceptable voltage limits.

Once the governing constraint is resolved, the calculator maps the required kW onto an industry-typical ladder of nameplate ratings and recommends the smallest ladder rung that covers the requirement. The headroom between the recommendation and the required kW is reported so the designer can see at a glance whether the selection sits comfortably within its rung or whether it is uncomfortably close to a ladder boundary.

The calculator supports preliminary sizing at the early design stage and more refined sizing once load schedules and equipment data sheets are available.

The voltage dip calculation in Section 4 uses the snapshot method described in IEEE Std 446-1995 §4.2.11 — the generator is modelled as a constant voltage source behind its transient reactance X'd. This method is appropriate for estimating the maximum instantaneous voltage dip during motor starting and for generator sizing purposes. For full motor acceleration studies or systems with multiple large motors starting sequentially, a transient stability simulation using dedicated power-system software is required.

2. Input Fields and Parameters

2.1 Project Title

Field Description Purpose
Project Title Free-text label for the generator sizing project Used as the filename stem when saving the project to device. Does not affect calculations.

2.2 Site and Generator Configuration

Field Options / Range Description Reference
System Voltage 120, 208, 240, 380, 400, 415, 480, 600, 4160, 13800 V Nominal line-to-line voltage of the distribution system the generator feeds. Used as the voltage base for the motor starting voltage dip calculation. —
Phases Single-phase / Three-phase System phase configuration. Affects the kVA-to-kW conversion relationship displayed in output panels. —
Generator Power Factor 0.8, 0.85, 1.0 The power factor at which the generator nameplate kVA rating is stated. Standard engine-generator sets are rated at 0.8 pf. The relationship kW = kVA × pf applies throughout the calculation. IEEE 446-1995 §4.2
Engine Type Naturally aspirated / Turbocharged Determines the altitude derating logic. Turbocharged engines maintain rated output up to a manufacturer-specified threshold altitude and only derate above it. Naturally aspirated engines begin derating from approximately sea level. IEEE 446-1995 §4.2.5
Turbo Derate Threshold 0–15,000 ft / 0–4,572 m (visible for turbocharged engines only) The altitude above which a turbocharged engine begins losing output. Default 3,000 ft. Obtain the exact value from the engine manufacturer's rating data. Typical range 2,500–5,000 ft (760–1,520 m). An inline unit selector toggles the input between feet and metres; the calculator normalises to feet internally for the IEEE 446-1995 derating formula. IEEE 446-1995 §4.2.5
Altitude 0–15,000 ft / 0–4,572 m above sea level Site elevation. Engine output decreases with altitude due to reduced air density and available oxygen for combustion. An inline unit selector toggles between feet and metres; the calculator normalises to feet internally. See Section 3.1 for the derating formula. IEEE 446-1995 §4.2.5
Ambient Temperature −40 to 140 °F / −40 to 60 °C Maximum expected ambient air temperature at the generator installation. Engine output decreases with increasing temperature above 60 °F (15.6 °C). An inline unit selector toggles between °F and °C; the calculator normalises to °F internally. See Section 3.1. IEEE 446-1995 §4.2.5
Design Margin 0–100 % (default 25 %) A contingency factor applied to the calculated running load kVA before nameplate selection. The margin accounts for future load growth, measurement uncertainty, and general engineering conservatism. Applied only to the running load constraint; motor starting and step load constraints are not further margined. —

2.3 Running Load Inventory

The load table accepts one row per load or load group. Each row represents a distinct type of load. The calculator sums all rows to compute total running demand. The table opens with five pre-populated example rows (Load 1 through Load 5) covering a range of load types; these are illustrative starting points and should be replaced with site-specific data. A maximum of 12 rows is supported. New rows added by the user via the + button default to Non-linear (VFD/UPS), 1 W, and are automatically labelled Load N, where N is one greater than the highest existing load number in the table. Each row accepts the load's power rating as a numeric value paired with an inline unit selector (W, kW, VA, kVA, or HP) — the calculator normalises the entered value to kW internally before applying efficiency, demand factor, quantity, and non-linear derating. Each row also carries two derived read-only columns — Power (kVAr) and Power (kVA) — that display the row's reactive and apparent power contribution computed from the editable inputs. Fields on each row are described below.

Column Options / Range Description
Description Free text User label for the load or load group. New rows are auto-labelled Load N; the label may be edited freely. Does not affect calculations.
Load Type Resistive / Induction motor / Synchronous motor / Non-linear (VFD/UPS) / Lighting / Other Controls which sub-fields are active. Selecting a motor type enables the Efficiency field. Selecting Non-linear enables the NL Derate field. Default power factor values are populated automatically based on load type.
Power Rating ≥ 0, with unit selector: W, kW, VA, kVA, HP The nameplate output power of the load, entered as a numeric value paired with an inline unit selector. For motors, enter the shaft output (mechanical) rating in W, kW, or HP. The calculator converts the entry to kW internally using fixed scale factors for the real-power units (1 W = 0.001 kW; 1 HP = 0.7457 kW) and a power-factor-dependent conversion for the apparent-power units (1 VA = PF ÷ 1000 kW; 1 kVA = PF × 1 kW), since VA and kVA express apparent power and must be multiplied by the row's power factor to yield real power. The internal kW value is then grossed up by the efficiency factor for motor loads. Changing the unit selection re-interprets the numeric value in the calculation but does not modify the number displayed in the input cell.
Power Factor (PF) 0.10–1.00 The running power factor of the load. Used to compute the kVA drawn. Default values: Resistive = 1.00; Induction motor = 0.85; Synchronous motor = 0.90; Non-linear = 0.80; Lighting = 0.90; Other = 0.85.
Efficiency (%) 1–100 % (motor loads only) Motor nameplate efficiency. Used to calculate electrical input kW from mechanical output kW: Input kW = Power Rating (kW) ÷ (Efficiency ÷ 100), where the Power Rating is the unit-normalised kW value from the preceding column. For non-motor loads, efficiency is fixed at 100 % and the field is disabled.
Demand Factor 0.0–1.0 (default 1.0) The ratio of actual running demand to connected kW. Accounts for the fact that not all loads operate simultaneously or at nameplate. Per IEEE 446-1995 §3.11.4.6, large computer system installations often exhibit demand factors of 0.75–0.85. Enter 1.0 if measured demand data is unavailable.
Quantity Integer ≥ 1 Number of identical loads represented by this row. Row contribution = (input kW per unit) × demand factor × quantity.
NL Derate (%) 0–50 % (non-linear loads only) Additional derating applied to account for harmonic currents generated by non-linear loads (VFDs, UPS systems, switched-mode power supplies). These harmonics cause additional heating in the alternator windings, effectively reducing the generator's usable output. The load's kW contribution is grossed up by the derate factor: Effective kW = Row kW ÷ (1 − NL Derate ÷ 100). Default 15 %.
Power (kVAr) Derived (read-only) Row reactive power contribution, computed as Row kVAr = Row kW × tan(cos−1(PF)). Reflects the row's post-efficiency, post-demand-factor, post-quantity, post-NL-derate value — the quantity that feeds the total running kVAr summation. Displays "—" when the Power Rating is zero.
Power (kVA) Derived (read-only) Row apparent power contribution, computed as Row kVA = √(Row kW² + Row kVAr²). For rows with efficiency and demand factor at 100 % and quantity 1, this simplifies to Power Rating (kW) ÷ PF. Displays "—" when the Power Rating is zero.

2.4 Motor Starting Inputs

The motor starting panel is a separate input block from the load table because it requires generator-specific parameters (X'd and voltage dip limit) that are not load properties. Only the single largest motor the generator must start is characterised here, and the calculator derives that motor's horsepower rating automatically from the load table — the largest row of type Induction motor or Synchronous motor is converted from its unit-normalised kW value to HP (1 kW ≈ 1.341 HP) and displayed as a read-only value. If no motor rows are present in the load table, the motor starting section falls inactive and contributes nothing to the governing result.

Field Options / Range Description Reference
Largest motor to start (HP) Derived (read-only) Horsepower rating of the single largest motor the generator must start, derived from the largest Induction motor or Synchronous motor row in the load table. An auto-tag beneath the field label indicates the source row kW and the computed HP (e.g. "22 kW → 29.5 HP"), or displays "no motor loads in table" when the table contains no motor rows. This is the motor that produces the greatest locked-rotor kVA demand and therefore the worst-case voltage dip. IEEE 446-1995 §4.2.11
Starting Method Across-the-line (DOL) / Soft starter / VFD / Star-delta / Autotransformer (65%) The motor starting method determines the fraction of full locked-rotor kVA that is actually presented to the generator bus. Selecting a method automatically populates the Starting Factor field with a typical value, which the user may override. IEEE 446-1995 §4.2.11
Starting Factor 0.05–1.00 (editable) Multiplier applied to the full DOL locked-rotor kVA to obtain the actual kVA demand presented to the generator. Default values by method: DOL = 1.00; Star-delta = 0.33; Soft starter = 0.35; Autotransformer (65%) = 0.42; VFD = 0.15. These are typical industry values; obtain exact values from the starter or drive manufacturer where precision is required. IEEE 446-1995 §4.2.11
NEMA Code Letter 3.0–22.4 kVA/hp (default 6.3) The locked-rotor kVA per horsepower value for the largest motor to be started. Enter the midpoint of the NEMA code letter band from the motor nameplate, or type any value directly if the manufacturer's datasheet provides an exact figure. Standard code letter midpoints are available as suggestions when the field is clicked. Default 6.3 kVA/hp (Code G, 5.6–6.29 kVA/hp), which is a conservative starting point for general-purpose induction motors when nameplate data is unavailable. NEMA MG-1
Generator X'd 0.05–0.60 p.u. (default 0.25) The transient reactance of the generator, in per-unit on the generator's own kVA base. Used in the snapshot voltage dip formula. Obtain from the generator manufacturer's data sheet. Typical values range from 0.20 to 0.35 p.u. for standard generator sets. A lower X'd means the generator is stiffer and will exhibit a smaller voltage dip for the same starting kVA. IEEE 446-1995 §4.2.11
Max Voltage Dip (Allowable bus dip) 5–40 % (default 20 %) Maximum acceptable instantaneous bus voltage dip during motor starting. The 20 % default is the widely accepted industry limit for adequate starting performance and bus equipment ride-through; IEEE 446-1995 § 4.2.11 notes that a sustained dip to 60–70 % of nominal can cause contactors and relays to drop out. IEEE 446-1995 §4.2.11

2.5 Step Load Acceptance Inputs

Field Options / Range Description Reference
Block Load (Largest single-step load) ≥ 0 kW / ≥ 0 W The largest block of load that can be energised in a single switching event — for example, a chiller plant, a lighting panel, or an entire emergency bus segment. This is the load that places the greatest instantaneous demand increase on the generator during restoration sequencing. An inline unit selector toggles between kW and W; the calculator normalises to kW internally. NFPA 110
Max Step Fraction (Max single-step kW, % of rated) 5–100 % (default 30 %) The maximum load block size the generator can accept in a single step, expressed as a percentage of its rated kW. The default of 30 % is the conventional limit for standard generator sets per NFPA 110. High-performance prime-power units with fast electronic isochronous governors may accept 50–100 % in a single step. Confirm the specific machine's step load acceptance capability with the manufacturer before setting a value above 30 %. NFPA 110

3. Calculation Methodology

3.1 Site Derating (IEEE 446-1995 §4.2.5)

Engine output decreases with both altitude and ambient temperature due to reduced combustion air density. The calculator applies derating factors derived from the rules stated in IEEE Std 446-1995 §4.2.5.

Altitude derating factor, falt

For naturally aspirated engines, derating begins from sea level:

falt = 1 − 0.04 × altitude (ft) ÷ 1000

For turbocharged engines, derating only begins above the manufacturer's specified threshold altitude hturbo:

falt = 1 − 0.04 × max(0, altitude − hturbo) ÷ 1000

The altitude derating rate of 4 % per 1,000 ft is stated explicitly in IEEE 446-1995 §4.2.5.

Temperature derating factor, ftemp

IEEE 446-1995 §4.2.5 states an average temperature derating of 1 % per 10 °F above a 60 °F baseline:

ftemp = 1 − 0.01 × max(0, Tambient − 60) ÷ 10

Combined derating factor

fcombined = falt × ftemp

The combined factor is applied to convert a required running-load output to the nameplate kVA that must be purchased: a generator derated to 90 % of nameplate at the installation site must have a nameplate 1 ÷ 0.90 = 1.111 times larger than the load it must serve at that site.

IEEE 446-1995 §4.2.5 notes that temperature derating is generally less significant than altitude derating. The standard also notes that turbocharged engines do not require derating below a minimum altitude that is typically in the range 2,500–5,000 ft, depending on the engine design. Always consult manufacturer rating data for the specific unit being sized.
The derating formulas above are stated in the native units of IEEE 446-1995 (feet, degrees Fahrenheit). The Altitude, Turbo Derate Threshold, and Ambient Temperature input fields each provide an inline unit selector for metric entry (m, °C). When a metric unit is selected, the calculator converts the input to the standard's native unit (altitude × 1 ÷ 0.3048 → ft; T°C × 9 ÷ 5 + 32 → °F) before applying the derating formulas. Results are numerically identical regardless of which unit the user enters.

3.2 Running Load Sizing

For each row in the load table, the calculator first normalises the user-entered power rating to kW, then computes an effective kW contribution that accounts for motor efficiency, demand factor, quantity, and non-linear derating.

Power rating normalisation

The power rating is entered as a numeric value Vrow paired with a unit selection. The real-power kW value used in all downstream formulas is:

Prated (kW) = Vrow × 0.001  (if unit = W)
Prated (kW) = Vrow  (if unit = kW)
Prated (kW) = Vrow × 0.7457  (if unit = HP)
Prated (kW) = Vrow × PF × 0.001  (if unit = VA)
Prated (kW) = Vrow × PF  (if unit = kVA)

The VA and kVA conversions multiply by the row's power factor because VA and kVA express apparent power (S); the calculator needs real power (P) as its downstream basis, and P = S × PF. The W, kW, and HP conversions are fixed-scale because these units already express real power directly.

Motor and synchronous motor loads:

Input kW = Prated ÷ (Efficiency ÷ 100)
Row kW = Input kW × Demand Factor × Quantity

Non-linear loads (VFD, UPS, switched-mode power supplies):

Row kW = (Prated × Demand Factor × Quantity) ÷ (1 − NL Derate ÷ 100)

All other load types:

Row kW = Prated × Demand Factor × Quantity

The total running kW, kVAr and kVA are then:

Total Running kW = Σ(Row kW for all rows)
Total Running kVAr = Σ(Row kW × tan(cos−1(PFi)))
Total Running kVA = √(Total Running kW² + Total Running kVAr²)

This vectorial summation correctly accounts for the fact that each load draws reactive current at its own power factor. The generator power factor (0.8 nameplate rating) is not used in this step — it defines only the nameplate kW:kVA ratio of the machine, not the load's reactive demand.

The design margin is applied to the running kVA:

Running kVA with margin = Total Running kVA × (1 + Design Margin ÷ 100)

The required nameplate kVA to satisfy the running load constraint (accounting for site derating) is:

kVAnameplate, running = Running kVA with margin ÷ fcombined

3.3 Motor Starting Voltage Dip (IEEE 446-1995 §4.2.11)

When a motor starts, it draws locked-rotor current that is typically 5–7 times its full-load current, at a power factor of 0.20–0.50 lagging. The resulting reactive power demand causes an instantaneous voltage dip on the generator bus. The magnitude of this dip depends on the motor's locked-rotor kVA, the starting method, and the generator's transient reactance X'd.

Step 1 — Full locked-rotor kVA (DOL equivalent)

LR kVA = Motor rating (hp) × NEMA code midpoint (kVA/hp)

Step 2 — LR kVA after starting method reduction

LR kVAreduced = LR kVA × Starting Factor

Step 3 — Snapshot voltage dip estimate

Per IEEE 446-1995 §4.2.11, the generator is modelled as a constant voltage source behind its transient reactance X'd. For a trial generator rating Sgen (kVA), the estimated voltage dip is:

Vdip (%) = [LR kVAreduced × X'd] ÷ [Sgen + LR kVAreduced × X'd] × 100

Step 4 — Minimum generator kVA to satisfy dip limit

Rearranging to find the minimum generator kVA that holds Vdip at or below the user's allowable limit:

Sgen, min = LR kVAreduced × X'd × (1 − Vdip,max) ÷ Vdip,max

where Vdip,max is the fractional dip limit (e.g. 0.20 for a 20 % limit).

Step 5 — Required nameplate kVA for motor starting (with derating)

kVAnameplate, motor = Sgen, min ÷ fcombined

3.4 Step Load Acceptance (NFPA 110)

The minimum generator running kVA that confines a given step load block to the allowable step fraction is:

Sgen, step = (Step Load kW ÷ Generator PF) ÷ (Max Step Fraction ÷ 100)

Applying site derating to find the required nameplate:

kVAnameplate, step = Sgen, step ÷ fcombined

3.5 Governing Result

The three nameplate kVA requirements are evaluated in parallel. The largest value governs:

kVArequired = max(kVAnameplate, running, kVAnameplate, motor, kVAnameplate, step)
kWrequired = kVArequired × Generator PF
kVArrequired = √(kVArequired2 − kWrequired2) = kVArequired × sin(cos−1(Generator PF))

The kVAr output expresses the reactive-power capability implied by the selected nameplate at the generator's rated power factor. The kW output is used when specifying the prime mover (engine) output; the kVAr output provides a sanity check that the total running kVAr demand sits comfortably inside the machine's reactive envelope.

Identifying the governing constraint indicates which design parameter drives the machine selection and therefore where design changes yield the greatest size reduction.

3.6 Recommended Standard Size

The required nameplate kW from Section 3.5 is the floor that the selected generator must meet or exceed. Commercial standby gensets are not produced at arbitrary continuous kW ratings — each manufacturer offers a discrete ladder of frame sizes. The Standby Planner recommends the smallest rung on an industry-typical ladder that meets or exceeds kWrequired:

kWrecommended = min{ kW ∈ L : kW ≥ kWrequired }

where L is the size ladder: 20, 25, 30, 35, 40, 50, 60, 80, 100, 125, 150, 175, 200, 230, 250, 275, 300, 350, 400, 450, 500, 550, 600, 650, 750, 800, 900, 1000, 1100, 1250, 1400, 1500, 1750, 2000, 2250, 2500, 2750, 3000 kW.

The equivalent nameplate kVA is then computed at the generator power factor:

kVArecommended = kWrecommended ÷ Generator PF

This ladder is a union of product catalogue rungs offered by major OEMs. It is not IEEE or NEMA standardised — different manufacturers skip or add rungs, particularly in the 500–1500 kW band, and the exact rating offered at each rung varies by engine/alternator pairing, fuel, and duty rating (standby, prime, or continuous). The recommendation is an engineering convenience for preliminary sizing; the final specification must be confirmed against the chosen manufacturer's current catalogue.

The headroom output reports the percentage and absolute kW margin between kWrecommended and kWrequired. A very tight headroom (below 10 %) indicates the required kW sits close to the top of the rung below — a single load growth event or change in site conditions could push the design above the selected rung. A large headroom (above 50 %) indicates a gap in the ladder has forced an oversized selection; consider whether the next rung down would satisfy the design with the margin reduced, or whether the selected rung has downrated variants available. Neither condition is a design fault — both are worth reviewing.

4. Output Fields

4.1 Site Derating Outputs

Output Units Description
Altitude derating factor falt p.u. Engine output fraction remaining after altitude derating. A value of 0.92 means the engine delivers 92 % of nameplate at the site altitude.
Temperature derating factor ftemp p.u. Engine output fraction remaining after temperature derating above the 60 °F baseline.
Combined derating factor fcombined p.u. Product of falt and ftemp. The nameplate kVA required is divided by this factor to account for the reduced output at the site conditions.

4.2 Running Load Outputs

Output Units Description
Total running kW kW Sum of all derated, demand-factored, efficiency-corrected kW contributions from the load table.
Total running kVAr kVAr Sum of all row reactive-power contributions, Σ(Row kWi × tan(cos−1(PFi))). This is the total reactive demand seen by the generator, expressed at the running-load operating point (not at the generator's nameplate power factor).
Total running kVA kVA Vectorial sum of all load apparent powers: √(ΣP² + ΣQ²), where each reactive component Qi = Row kWi × tan(cos−1(PFi)). This is the actual apparent power demand presented to the generator bus, accounting for each load's individual power factor. Note: this quantity is independent of the generator's rated power factor (0.8); the generator nameplate PF defines the machine's kW:kVA ratio, not the load's reactive demand.
Running kVA (with margin) kVA Total running kVA multiplied by (1 + Design Margin ÷ 100). The margin provides headroom for load growth and measurement uncertainty.
Req. Running nameplate kVA kVA Running kVA with margin divided by the combined derating factor. This is the nameplate kVA that the running load constraint alone requires, before comparing against motor starting and step load constraints.

4.3 Motor Starting Outputs

Output Units Description
LR kVA — Terminals kVA Full locked-rotor kVA demand if the motor were started DOL, computed from motor hp and NEMA code letter midpoint.
LR kVA after starting method reduction kVA The locked-rotor kVA demand actually presented to the generator bus after applying the starting method factor. This is the value used in the voltage dip formula.
Estimated voltage dip % The voltage dip estimated at the running-load nameplate kVA, using the snapshot formula. Flagged amber if > 15 % and red if it exceeds the user-defined maximum. A dip within the maximum limit means the running-load-sized generator is also adequate for motor starting.
Min. generator kVA for dip limit kVA The minimum nameplate kVA required to hold the bus voltage dip within the user's maximum allowable dip, accounting for site derating.

4.4 Step Load Output

Output Units Description
Step load min. kVA (at nameplate) kVA The minimum nameplate kVA required to keep the specified step load block within the maximum allowable step fraction, after site derating.

4.5 Governing Result Outputs

Output Units Description
Min. required nameplate kW kW Min. required nameplate kVA multiplied by the generator power factor. Used when specifying prime mover (engine) output power.
Min. required nameplate kVAr kVAr Reactive-power capability of the required nameplate, computed at the generator's nameplate power factor as √(kVArequired² − kWrequired²). Useful as a cross-check that the selected machine's reactive capability envelops the total running kVAr demand.
Min. required nameplate kVA kVA The largest of the three constraint-specific nameplate kVA values. This is the minimum generator nameplate kVA the machine must meet or exceed. The Recommended Size subsection below converts this floor to the next ladder rung automatically.
Governing constraint — Identifies which of the three constraints produced the largest kVA requirement: Running load (green), Motor starting (amber), or Step load (blue). Use this to guide design decisions — if motor starting governs, evaluate whether a soft starter or VFD on the largest motor would reduce the required generator size.
Next standard nameplate kW kW The smallest rung on the industry-typical size ladder at or above kWrequired. See Section 3.6 for the full ladder and its basis.
Equivalent nameplate kVA kVA The recommended kW divided by the generator power factor. At the default 0.8 PF this equals kW × 1.25; at unity PF it equals the kW value.
Headroom above required % & kW Percentage and absolute margin between kWrecommended and kWrequired. Tight headroom (below 10 %) is flagged amber — review design margins and check whether a design margin increase is warranted. Large headroom (above 50 %) is also flagged amber — a ladder gap has forced oversizing and the next rung down may be worth evaluating with downrated variants.

4.6 Parameter Status Checks

Check Status Levels Description
Load inventory OK / Warning / — Confirms that the load table contains at least one row with a non-zero kW value, and that all demand factors and power factors are within physical limits.
Altitude derating OK Reports the entered altitude for confirmation, echoed in the user's selected unit (ft or m).
Temperature derating OK / Warning Flags amber when the ambient temperature exceeds the 60 °F (15.6 °C) baseline, indicating that temperature derating has been applied. The status message echoes both the entered value and the baseline in the user's selected unit (°F or °C).
Motor starting voltage dip OK / Error / — Compares the estimated voltage dip at the running-load nameplate kVA against the user's maximum allowable dip. Flags red if the dip exceeds the limit, indicating that motor starting governs and a larger machine is required.
Step load acceptance OK / — Confirms step load data has been entered. The status message echoes the entered block size in the user's selected unit (kW or W).
Generator X'd range (0.10–0.50) OK / Warning Flags amber if the entered transient reactance falls outside the typical range for standard generator sets. Values outside 0.10–0.50 p.u. should be verified against the specific manufacturer's data sheet.

5. NEMA Code Letter Reference

NEMA MG-1 defines motor code letters indicating locked-rotor kVA per horsepower. The calculator uses the midpoint of each band in the locked-rotor kVA calculation.

Code Letter kVA/hp Range Midpoint Used Notes
A 0 – 3.14 3.15 * Very low starting kVA; uncommon in general-purpose motors
B 3.15 – 3.54 3.55 *
C 3.55 – 3.99 4.0 *
D 4.0 – 4.49 4.5 *
E 4.5 – 4.99 5.0 *
F 5.0 – 5.59 5.3
G 5.6 – 6.29 6.3 Default. Conservative selection for general-purpose motors when nameplate is unavailable.
H 6.3 – 7.09 7.1 *
J 7.1 – 7.99 8.0 *
K 8.0 – 8.99 9.0 *
L 9.0 – 9.99 10.0 *
M 10.0 – 11.19 11.2 *
N 11.2 – 12.49 12.5 * High starting kVA; compressors and other high-inertia loads
P 12.5 – 13.99 14.0 *
R 14.0 – 14.99 15.0 *
S 15.0 – 16.99 17.0 *
T 17.0 – 18.99 19.0 *
U 19.0 – 21.19 21.2 *
V 21.2 and above 22.4 * Very high starting kVA; wound-rotor or special-duty motors

* Upper boundary of range used as midpoint approximation where the band is open-ended or the midpoint is very close to the upper boundary.

6. Limitations and Best Practices

6.1 Known Limitations

  • The voltage dip calculation uses the IEEE 446-1995 snapshot method (constant voltage behind X’d), which does not model governor and AVR dynamics during motor acceleration. For systems with multiple large motors starting in sequence, or where precise dip prediction is required, a transient stability simulation is necessary.
  • The motor starting section models only the single largest motor. Simultaneous starting of multiple motors is not assessed. If two large motors may start simultaneously, size the calculator inputs to represent their combined locked-rotor kVA on a single equivalent motor entry.
  • Derating factors are derived from the rules in IEEE 446-1995 §4.2.5, which are average engineering guidelines. Specific engine models deviate from these averages. Always verify final derating against the engine manufacturer's altitude and temperature correction curves for the specific unit being procured.
  • The calculator does not account for harmonic voltage distortion on the generator bus caused by large non-linear loads. For installations where non-linear load content is high (greater than 30 % of total kVA), a generator with a 2/3-pitch or 12-pitch alternator winding designed to suppress triplen harmonics should be specified, and the generator manufacturer's specific harmonic derating guidance should be applied.
  • Power factor of individual loads is entered as a single value per row. The calculator does not perform a phasor summation of individual load kVA components. For high-precision studies, a full load flow analysis is recommended.
  • Parallel generator sets and generator-to-generator synchronising requirements are not addressed. The calculator sizes a single generator serving the total load.

6.2 Best Practices

  • At the preliminary design stage, Code G is a reasonable default NEMA code letter for general-purpose induction motors. Refine to the actual nameplate code letter as equipment submittals become available.
  • Always obtain the generator transient reactance X'd from the specific manufacturer's data sheet for final sizing. A default of 0.25 p.u. is a reasonable placeholder for preliminary work.
  • If motor starting governs the generator selection, evaluate the cost trade-off between a larger generator and soft starters or VFDs on the governing motors. A soft starter reducing the starting factor from 1.00 (DOL) to 0.35 can reduce the motor starting kVA demand by 65 %, often making motor starting the non-governing constraint.
  • For critical or emergency systems (Level 1 per NFPA 110), use a design margin of at least 25 % to provide headroom for future load additions and to ensure reliable starting of the generator under worst-case conditions.
  • Conduct measurements during peak load periods when validating the running load inventory against an existing facility. Connected nameplate loads can significantly overstate actual running demand; measured demand factors of 0.70–0.85 are common in commercial buildings.
  • Review NFPA 110-2025 requirements for minimum fuel storage, automatic transfer switch functionality, and periodic load testing requirements for the emergency power classification applicable to the facility. Note that NFPA 110-2025 §5.5.3 introduced a two-tier fuel tank capacity rule: for EPSS Class ≤ 24 h the main fuel tank must hold at least 133 % of the low-fuel sensor setpoint; for Class > 24 h (Class 48, 72, 96, etc.) the minimum drops to 100 % of the low-fuel sensor setpoint.

7. Worked Examples

The following examples illustrate the three-constraint sizing process and show how the governing constraint varies with load mix and site conditions.

Each load's Power Rating is stated directly in kW for clarity. In the calculator UI the same value can be entered in any supported unit — for example, 15 kW as "15" with the kW selector, as "15000" with the W selector, as "20.1" with the HP selector, or as an apparent-power value with the VA or kVA selector (in which case the calculator multiplies by the row's power factor to obtain real power). The downstream calculation is identical regardless of which unit the user enters, so the numeric steps below apply unchanged.

7.1 Example 1 — Commercial Office Building, Sea Level

A standby generator is to serve the essential loads of a four-storey commercial office building. The site is at sea level with a maximum ambient temperature of 95 °F. The load schedule is as follows.

Given — Site and generator configuration:

  • System voltage: 480 V, three-phase
  • Generator power factor: 0.8
  • Engine type: Naturally aspirated
  • Altitude: 0 ft
  • Ambient temperature: 95 °F
  • Design margin: 25 %

Given — Load inventory:

  • HVAC air handlers (induction motor, 3 × 15 kW, PF 0.85, eff. 90 %, dem. factor 0.9): three units
  • Emergency lighting (lighting, 12 kW, PF 0.90, dem. factor 1.0): one group
  • Server room UPS (non-linear, 30 kW, PF 0.80, NL derate 15 %, dem. factor 1.0): one unit
  • Fire pump (induction motor, 37 kW, PF 0.85, eff. 92 %, dem. factor 1.0): one unit

Given — Motor starting (largest motor is the fire pump at 50 hp):

  • Motor rating: 50 hp
  • Starting method: Across-the-line (DOL), starting factor 1.00
  • NEMA code: G (6.3 kVA/hp)
  • Generator X'd: 0.25 p.u.
  • Maximum allowable voltage dip: 20 %

Given — Step load:

  • Largest single-step load: 37 kW (fire pump)
  • Max step fraction: 30 %

Step 1 — Site Derating

falt = 1 − 0.04 × 0 ÷ 1000 = 1.000

Excess temperature = 95 − 60 = 35 °F
ftemp = 1 − 0.01 × 35 ÷ 10 = 1 − 0.035 = 0.965

fcombined = 1.000 × 0.965 = 0.965

Step 2 — Running Load

HVAC air handlers: Input kW = 15 ÷ 0.90 = 16.67 kW; Row kW = 16.67 × 0.9 × 3 = 45.0 kW
Emergency lighting: Row kW = 12 × 1.0 × 1 = 12.0 kW
Server room UPS: Row kW = (30 × 1.0 × 1) ÷ (1 − 0.15) = 30 ÷ 0.85 = 35.3 kW
Fire pump: Input kW = 37 ÷ 0.92 = 40.2 kW; Row kW = 40.2 × 1.0 × 1 = 40.2 kW

Total Running kW = 45.0 + 12.0 + 35.3 + 40.2 = 132.5 kW

Reactive components (Q = P × tan(cos−1(PF))):
HVAC (PF 0.85): Q = 45.0 × tan(cos−1(0.85)) = 45.0 × 0.6197 = 27.9 kVAr
Lighting (PF 0.90): Q = 12.0 × tan(cos−1(0.90)) = 12.0 × 0.4843 = 5.8 kVAr
UPS (PF 0.80): Q = 35.3 × tan(cos−1(0.80)) = 35.3 × 0.7500 = 26.5 kVAr
Fire pump (PF 0.85): Q = 40.2 × tan(cos−1(0.85)) = 40.2 × 0.6197 = 24.9 kVAr
Total kVAr = 27.9 + 5.8 + 26.5 + 24.9 = 85.1 kVAr

Total Running kVA = √(132.5² + 85.1²) = √(17556 + 7242) = √24798 = 157.5 kVA
Running kVA with margin = 157.5 × 1.25 = 196.9 kVA
kVAnameplate, running = 196.9 ÷ 0.965 = 204.0 kVA

Step 3 — Motor Starting

LR kVA = 50 × 6.3 = 315 kVA
LR kVAreduced = 315 × 1.00 = 315 kVA (DOL)

Vdip,max = 0.20
Sgen, min = 315 × 0.25 × (1 − 0.20) ÷ 0.20 = 63.0 ÷ 0.20 = 315 kVA

kVAnameplate, motor = 315 ÷ 0.965 = 326.4 kVA

Step 4 — Step Load

Sgen, step = (37 ÷ 0.8) ÷ (0.30) = 46.25 ÷ 0.30 = 154.2 kVA
kVAnameplate, step = 154.2 ÷ 0.965 = 159.8 kVA

Step 5 — Governing Result

kVArequired = max(204.0, 326.4, 159.8) = 326.4 kVA

Governing constraint: Motor starting
kWrequired = 326.4 × 0.8 = 261.1 kW
kVArrequired = √(326.4² − 261.1²) = √(106,537 − 68,173) = √38,364 = 195.9 kVAr

Step 6 — Recommended Size

kWrequired = 261.1 kW

Ladder search: smallest rung ≥ 261.1 kW → 275 kW (ladder rungs 250, 275, 300)
kWrecommended = 275 kW
kVArecommended = 275 ÷ 0.8 = 343.75 kVA

Headroom = (275 − 261.1) ÷ 261.1 × 100 = 5.3 % (13.9 kW)

The fire pump DOL start drives the selection. Specify a 275 kW / 343.75 kVA generator set as the smallest ladder rung that meets the motor starting constraint. The 5.3 % headroom is tight — flagged amber by the calculator — so the designer should either accept the narrow margin or step up to the next rung (300 kW / 375 kVA) to preserve future load growth capacity. If the fire pump were fitted with a soft starter (starting factor 0.35), the motor starting constraint would reduce to 114.2 kVA nameplate, making running load the governing constraint at 204.0 kVA (163.2 kW) — allowing a 175 kW / 218.75 kVA unit to be specified instead, a 100 kW reduction.

Calculator Results Summary:

Parameter Value Units
Total running kW 132.5 kW
Total running kVAr 85.1 kVAr
Total running kVA 157.5 kVA
Running kVA with margin (25 %) 196.9 kVA
Combined derating factor 0.965 p.u.
Req. Running nameplate kVA 204.0 kVA
LR kVA — Terminals (DOL) 315.0 kVA
Required nameplate kVA (motor starting) 326.4 kVA
Required nameplate kVA (step load) 159.8 kVA
Min. required nameplate kW 261.1 kW
Min. required nameplate kVAr 195.9 kVAr
Min. required nameplate kVA 326.4 kVA
Governing constraint Motor starting
Next standard nameplate kW 275 kW
Equivalent nameplate kVA 343.75 kVA
Headroom above required +5.3 % (13.9 kW) — tight

7.2 Example 2 — High-Altitude Industrial Facility

A standby generator is to serve critical process loads at an industrial facility located at 6,500 ft altitude with maximum ambient temperature of 104 °F. No motors above 5 hp are on the critical bus. The step load concern is a large electric heater bank that must energise as a single block.

Given — Site and generator configuration:

  • System voltage: 480 V, three-phase
  • Generator power factor: 0.8
  • Engine type: Turbocharged, turbo threshold 3,000 ft
  • Altitude: 6,500 ft
  • Ambient temperature: 104 °F
  • Design margin: 25 %

Given — Load inventory:

  • Process instrumentation (resistive, 18 kW, PF 1.0, dem. factor 1.0): one group
  • Control room HVAC (induction motor, 7.5 kW, PF 0.85, eff. 88 %, dem. factor 1.0): one unit
  • DCS servers (non-linear, 20 kW, PF 0.80, NL derate 15 %, dem. factor 1.0): one group
  • Process lighting (lighting, 6 kW, PF 0.90, dem. factor 1.0): one group

Given — Motor starting:

  • Motor rating: 10 hp (control room HVAC compressor)
  • Starting method: Across-the-line (DOL), starting factor 1.00
  • NEMA code: G (6.3 kVA/hp)
  • Generator X'd: 0.28 p.u.
  • Maximum allowable voltage dip: 20 %

Given — Step load:

  • Largest single-step load: 40 kW (electric heater bank)
  • Max step fraction: 30 %

Step 1 — Site Derating

Turbocharged engine, threshold 3,000 ft; effective altitude = 6,500 − 3,000 = 3,500 ft
falt = 1 − 0.04 × 3,500 ÷ 1,000 = 1 − 0.14 = 0.860

Excess temperature = 104 − 60 = 44 °F
ftemp = 1 − 0.01 × 44 ÷ 10 = 1 − 0.044 = 0.956

fcombined = 0.860 × 0.956 = 0.822

Step 2 — Running Load

Process instrumentation: 18.0 × 1.0 × 1 = 18.0 kW
Control room HVAC: (7.5 ÷ 0.88) × 1.0 × 1 = 8.52 kW
DCS servers: (20 × 1.0 × 1) ÷ 0.85 = 23.5 kW
Process lighting: 6.0 × 1.0 × 1 = 6.0 kW

Total Running kW = 18.0 + 8.52 + 23.5 + 6.0 = 56.0 kW

Reactive components (Q = P × tan(cos−1(PF))):
Instrumentation (PF 1.0): Q = 18.0 × 0 = 0.0 kVAr
HVAC (PF 0.85): Q = 8.52 × tan(cos−1(0.85)) = 8.52 × 0.6197 = 5.3 kVAr
DCS servers (PF 0.80): Q = 23.5 × tan(cos−1(0.80)) = 23.5 × 0.7500 = 17.6 kVAr
Lighting (PF 0.90): Q = 6.0 × tan(cos−1(0.90)) = 6.0 × 0.4843 = 2.9 kVAr
Total kVAr = 0.0 + 5.3 + 17.6 + 2.9 = 25.8 kVAr

Total Running kVA = √(56.0² + 25.8²) = √(3136 + 666) = √3802 = 61.7 kVA
Running kVA with margin = 61.7 × 1.25 = 77.1 kVA
kVAnameplate, running = 77.1 ÷ 0.822 = 93.8 kVA

Step 3 — Motor Starting

LR kVA = 10 × 6.3 = 63.0 kVA (DOL)
Sgen, min = 63.0 × 0.28 × (1 − 0.20) ÷ 0.20 = 14.112 ÷ 0.20 = 70.56 kVA
kVAnameplate, motor = 70.56 ÷ 0.822 = 85.8 kVA

Step 4 — Step Load

Sgen, step = (40 ÷ 0.8) ÷ 0.30 = 50.0 ÷ 0.30 = 166.7 kVA
kVAnameplate, step = 166.7 ÷ 0.822 = 202.8 kVA

Step 5 — Governing Result

kVArequired = max(93.8, 85.8, 202.8) = 202.8 kVA

Governing constraint: Step load
kWrequired = 202.8 × 0.8 = 162.2 kW
kVArrequired = √(202.8² − 162.2²) = √(41,128 − 26,309) = √14,819 = 121.7 kVAr

Step 6 — Recommended Size

kWrequired = 162.2 kW

Ladder search: smallest rung ≥ 162.2 kW → 175 kW (ladder rungs 150, 175, 200)
kWrecommended = 175 kW
kVArecommended = 175 ÷ 0.8 = 218.75 kVA

Headroom = (175 − 162.2) ÷ 162.2 × 100 = 7.9 % (12.8 kW)

In this example the step load governs — the electric heater bank energising as a single block drives the selection despite the relatively modest running load. The severe site derating (fcombined = 0.822) also makes a significant contribution: the nameplate kVA must be about 22 % larger than the load it serves at sea level equivalent. Specify a 175 kW / 218.75 kVA generator set as the smallest ladder rung meeting the step load constraint. The 7.9 % headroom is tight — flagged amber by the calculator — so the 200 kW / 250 kVA rung may be preferable if future heater capacity or other step loads are anticipated. If the heater bank can be split across two contactors with a sequencing delay, the step load constraint halves and running load becomes governing at 93.8 kVA (75.0 kW), allowing an 80 kW / 100 kVA unit — a 95 kW reduction.

Calculator Results Summary:

Parameter Value Units
Combined derating factor 0.822 p.u.
Total running kW 56.0 kW
Total running kVAr 25.8 kVAr
Total running kVA 61.7 kVA
Req. Running nameplate kVA 93.8 kVA
Required nameplate kVA (motor starting) 85.8 kVA
Required nameplate kVA (step load) 202.8 kVA
Min. required nameplate kW 162.2 kW
Min. required nameplate kVAr 121.7 kVAr
Min. required nameplate kVA 202.8 kVA
Governing constraint Step load
Next standard nameplate kW 175 kW
Equivalent nameplate kVA 218.75 kVA
Headroom above required +7.9 % (12.8 kW) — tight

Additional Examples

The following published articles contain worked numerical generator sizing examples and may be useful as supplementary study material.

8. References

  • IEEE Std 446-1995, IEEE Recommended Practice for Emergency and Standby Power Systems for Industrial and Commercial Applications (Orange Book)
  • NFPA 110-2025, Standard for Emergency and Standby Power Systems
  • NFPA 70-2026 (NEC), National Electrical Code, Article 700 (Emergency Systems), Article 701 (Legally Required Standby Systems), Article 702 (Optional Standby Systems), Article 445 (Generators) — article numbers unchanged from 2023 edition
  • NEMA MG-1-2021, Motors and Generators (Code Letter definitions, Part 10)
  • IEEE Std 141-1993, IEEE Recommended Practice for Electric Power Distribution for Industrial Plants (Red Book)
  • EGSA 101P-2006, Performance Standard for Engine Driven Generator Sets
  • ISO 8528-1:2018, Reciprocating internal combustion engine driven alternating current generating sets — Part 1: Application, ratings and performance